5.4.10 Sprint report
Pre-condition:
A sprint must be ended.
Only Project Admin or Project Moderator can see a sprint report.
The sprint report contains the sprint overview and the sprint completed report.
Sprint Completed report:
It shows the full sprint report after a sprint is ended.
Here you can see,
Sprint duration (actual start date - actual end date)
Summary (completed task number, incompleted task number, Story Points earned against the total story points)
Total task numbers
Total task number of the new sprint
Total task numbers that were added from the old sprint
Total task numbers that were added during the sprint run
Dependency task numbers
Progress
Teammates number
Team Progress graph (status-wise task number)
Sprint-wise team velocity graph (expected vs earned)
Leaderboard (on the basis or earned story points)
Task burndown graph (ideal vs actual)
Effort burndown graph (ideal vs actual)
Process:
Go to the Sprint section & choose the completed sprint.
You will see 2 icons on the left of “Completed.”
Click the right-side icon. Here you will see the full report of a sprint.
Last updated