# 5.4.10 Sprint report

### Pre-condition:

* A sprint must be ended.
* Only Project Admin or Project Moderator can see a sprint report.

The sprint report contains the sprint overview and the sprint completed report.&#x20;

### Sprint Completed report:&#x20;

It shows the full sprint report after a sprint is ended.&#x20;

Here you can see,

* Sprint duration (actual start date - actual end date)
* Summary (completed task number, incompleted task number, Story Points earned against the total story points)
* Total task numbers
* Total task number of the new sprint
* Total task numbers that were added from the old sprint
* Total task numbers that were added during the sprint run
* Dependency task numbers
* Progress
* Teammates number
* Team Progress graph (status-wise task number)
* Sprint-wise team velocity graph (expected vs earned)
* Leaderboard (on the basis or earned story points)
* Task burndown graph (ideal vs actual)
* Effort burndown graph (ideal vs actual)

### Process:

* Go to the Sprint section & choose the completed sprint.
* You will see 2 icons on the left of “Completed.”
* Click the right-side icon. Here you will see the full report of a sprint.

<figure><img src="https://lh5.googleusercontent.com/OmU4pPCckV5lzytNRNtu8hBYL_qWvQS_j8eQy41OmAxXP886SI4_fc7lC1dSudpNFIg_57DfAm80ZJeHh944qrObM6BgTZnSFS3ln0nfFT80x_UaoS6YuexCoB-SLPGugcbgE1HHo6CLcoja8y5KPHcH6G8R966q4CzIyS6R6fMRmg_AziejOgF1hrRQGA" alt=""><figcaption></figcaption></figure>

<br>
